Our Pelican Plan home is almost complete.  Should be listed and for sale within the next week.  Call Steve @ 239-410-0140 with questions or for your private viewing.

Coming Soon.  Watch the progress of this home as it is built Carney Quality.  Our very popular Pelican plan home.  3 Bedrooms, 2 bathrooms, 3-car garage.  Great floor plan.  We build our Carney homes with extra features that help make our Carney homes stronger and higher in quality then most of our competitors.

Underground plumbing/electrical in.  Out for inspections.  Next, pre-treatment for bugs and prep for slab to be poured.  Water and Sewer hookup completed.  Slab has been poured as well as inspections completed.  Will start moving fast from here.

Latest pictures show walls going up, Lintels in over doors and windows and tie beam forming next.  Tie Beam formed.  Trusses in and plywood, (not OSB), roof going on.  Framing started.  Framing complete, rough plumbing going in and A/C duct going in.

HVAC, rough plumbing, rough electrical completed.  Next are inspections for all three of these items and then we move to the next steps in the building process.

Shingles have been completed on roof and doors are going in.  Windows and sliders have been installed.

Front Doors have been installed.  Insulation, we use R38 in the ceiling vs. everyone else that uses R30.  The framing and insulation inspections have been completed and passed.  Stucco and drywall is going in next.  Wall texture is complete and interior painting has began.

Tile flooring has been installed, and please see that we have tile where the cabinets will be installed.  Just another nice feature we add to our home builds.

Cabinet construction has began, with tile under the cabinets.

Driveway and walkway have been poured.  Bathroom wall tile is in progress.  Pool and lanai pavers have been installed.  Inside and outside painting in ongoing.  Looking Good!

Countertops have been installed and getting the interior of the home prepped for final painting.